If the job contains a flat slab overhanging from an internal joist floor slab, the reinforcement of the beam without torsional effects, although these do not really occur, can be known. If the top reinforcement and infilling of the concrete is done as described in the construction details, copy the job and substitute the slab with an equivalent line load applied on the beam. Add the overhanging slab in the drawing later on.